Projects Closed flare unit UFBG

Year
2021
Category
Flare systems

Installation of thermal insulation internal layers and staged burner system of closed flare unit UFBG has been completed.

The maximum capacity by combusted gases will be over 285 tons/hour.

The height of the plant is 44 meters, the diameter of the combustion chamber is 19 meters, the diameter of the wind and noise fence is 26 meters.

Would you like to discuss your project?

Our team is ready to implement a project of any complexity.
If you have assignments or questions, leave a request and we will contact you as soon as possible

Other projects
2021 year
Fuel gas treatment unit is designed for preparation of fuel gas for the boiler unit of UKPG-1, gas for the methanol regeneration unit, gas for the flare system VD, ND, and UGG (purification, heating, flow measurement, and gas pressure reduction before supplying to the consumer).
2018 year
The water pumping station has been commissioned.
2022 year
Bunter Group has completed installation of one of the two 019-P-1.1 and 019-P-1.2 furnace units manufactured for the condensate de-ethanization unit.
2021 year
Heaters PNPT-3.87 designed to heat oil and their mixtures in the system of collection, transportation, and preparation of well products has been manufactured and shipped to the Customer.
2020 year
Gas treatment unit for auxiliaries is designed for purification, heating, and reduction of natural gas pressure of main gas pipelines to the required pressure and maintaining it with a specified accuracy before supplying to the consumer.

На этом веб-сайте используются файлы cookie, которые обеспечивают работу всех функций для наиболее эффективной навигации по странице. Если вы не хотите принимать постоянные файлы cookie, пожалуйста, выберите соответствующие настройки на своем компьютере. Продолжая навигацию по сайту, вы предоставляете свое согласие на использование файлов cookie на этом веб-сайте. Более подробная информация предоставляется в нашей политике конфиденциальности