Bunter Group has completed installation of one of the two 019-P-1.1 and 019-P-1.2 furnace units manufactured for the condensate de-ethanization unit. The furnaces are designed for heating and evaporation of light fractions in gas condensate. The capacity of the unit is up to 277,000 kg per hour. The useful heat output of the furnaces is 13.7 MW.

The furnace was started up on June 13. After concrete drying, the furnace operates at temperatures and flow rates higher than nominal modes, providing the de-ethanization column with raw materials of necessary specifications. The actual efficiency of the furnace corresponds to the calculated values.

Cylinder furnaces manufactured by the Bunter Group are supplied to the customer with fuel gas preparation units, inlet product lines, and outlet product lines. Frame valve blocks provide fuel gas supply to pilot and main burners, its reduction, flow measurement, and purification from mechanical impurities. Product line units ensure that the product is evenly distributed across the two coil streams.

The pipeline connection between furnaces and control system with process controller and emergency protection controller allows the furnace to be operated safely in accordance with federal standards and regulations.

Would you like to discuss your project?

Our team is ready to implement a project of any complexity.
If you have assignments or questions, leave a request and we will contact you as soon as possible

Other projects
2019 year
The Customer faced a non-standard task: oil emulsion needed to be heated directly from the well pad in the absence of prepared fuel gas to feed the heater burners and the remaining infrastructure around the well pad.
2021 year
Newly designed indirect heater has been manufactured and shipped to the Customer.
2016 year
Flare unit designed for high-efficiency and high-quality combustion of periodic, permanent, and emergency discharges of combustible gases at oil and gas field treatment facilities in oil and gas fields, as well as oil, gas, and petrochemical industry enterprises, has been manufactured and shipped to the Customer.
2018 year
The water pumping station has been commissioned.
2020 year
Gas treatment unit for auxiliaries is designed for purification, heating, and reduction of natural gas pressure of main gas pipelines to the required pressure and maintaining it with a specified accuracy before supplying to the consumer.

На этом веб-сайте используются файлы cookie, которые обеспечивают работу всех функций для наиболее эффективной навигации по странице. Если вы не хотите принимать постоянные файлы cookie, пожалуйста, выберите соответствующие настройки на своем компьютере. Продолжая навигацию по сайту, вы предоставляете свое согласие на использование файлов cookie на этом веб-сайте. Более подробная информация предоставляется в нашей политике конфиденциальности